Certified company | Engineering the world

00353 (0)719633222

Get in touch

Water Treatment

Ballycar Group Water Scheme

Project Description

Creating and testing of group water scheme supply at Ballycar Co. Clare.

Client

Clare County Council

Project Value

€1.05 million.

Key Features

  • Works carried out under a Road Closure to the L7188 Road.
  • Road opening license obtained from Clare County Council.
  • Maintain traffic management through the course of the works
  • Waste carrier license to dispose of acceptable material to a licensed tip
  • Upgrade works to an existing group water scheme located at Ballycar, Co. Clare
  • Removal of 4.1km of the existing mains and the replacement of same with a new 110mm HPPE watermain in rocky ground
  • Welding joints and testing of welds at regular intervals
  • Installation of Sluice Valves, Air Valves, Fire Hydrants.
  • 65nr saddle connections with a 25mm water pipe to a boundary box and consumer meters
  • Installation of a Kiosks containing a bulk meter and network logger
  • Hydrostatic Testing and chlorinating the watermain to Irish Water Standards
  • Temporary and permanent reinstatement of the trench
  • Double surface dressing of the road on completion of the works
  • Preparation and handover of the safety file on completion of the safety file
Civil engineering project Ballycar group water scheme.
Civil engineering project Ballycar group water scheme.
Civil engineering project Ballycar group water scheme.
Civil engineering project Ballycar group water scheme.

let’s get connected

Have a Question?

If you have a question about our projects or would like more information on what we can do for you, why not get in touch?